EXTERNAL REFURBISHMENT CONSISTING OF;
Roof Oversheet
Installing Plastisol Coated Galvanised Sheeting, fixed to 250mm- standing bracket with appropriate fixings and seal washers. The support bars channel section were fixed to the support brackets and then fixed to the existing roof structure on to the existing steelwork with galvanised fixings. Inclusive of GRP skylights over existing GRP skylights (approximately 10% of roof area).
All works were carried out in line with Health and Safety Regulations Work Act 1974 and the (CAR 2012) Control of Asbestos Regulations 2012
Lane Roofing installed insulation quilt laid within the cavity between the old and new system. To meet current building Regulations Part L October 2010.We also installed closures, flashings, ridge section and filler details to form a fully Weather-Tight Roofing System.
Steel Gutter
Enhancement to ensure waterflows and outlets were adequate for the roof size.
PROJECT OVERVIEW;
Ellisons Coventry oversheeting project took 16 weeks from start to finish, with 4 roofing specialists on site for the duration of the project.
BEFORE:
AFTER: